Did the City answer the comments?

Hundreds of people wrote to the City. This page compares what they asked with what the City answered.

The City split the letters into 882 issues

  • About 203 letters came during the draft Environmental Impact Statement comment period, from December 18, 2025 through March 5, 2026.
  • That was months before the revised maps came out on August 7.
  • The letters are one part of the larger PlanSpokane public-comment record.
504rows point to 11 general answers
173rows say "Comment noted"
41rows say "forwarded to decision-makers"

Some rows fit more than one category. The City also revised material on Tribal history, water, fire response, and transportation.

The test is simple. Did the City answer the question? Did it change the plan? If not, who decides next?


What would a clear answer say?

Each card shows the question, the City's reply, and what a direct answer could include. The green lists are examples, not City commitments.

Trees and environmental review

What people asked: Will development and environmental-review exemptions remove more trees? Will they push the City's 30% canopy goal farther away?

What the City said: The City points all four comments to one broad answer. It lists possible steps. Those include more SpoCanopy resources, incentives, land purchases, code changes, and tree-preservation incentives. It does not give today's canopy, expected losses, or a path to 30% by 2030.

A clearer answer would say:

  1. Measure today's tree canopy in every neighborhood.
  2. Estimate losses from fires and development.
  3. Name the work, funding, deadlines, and departments needed to reach 30% by 2030.
  4. Protect neighborhoods with the least canopy from further loss.

Transportation

What people asked: The state transportation department says some state facilities will exceed capacity. It questions the City's growth model. It wants more analysis before environmental-review exemptions move forward.

What the City said: The City says no exemption code has been written. It points to concurrency rules, impact fees, and added appendices. The state says information is still missing. The City points back to earlier answers.

A clearer answer would say:

  1. Name the highways and intersections expected to exceed capacity.
  2. Show what model data the state requested, what changed, and what is still disputed.
  3. List the needed projects, costs, funding, builders, and triggers.
  4. State what must be resolved before an exemption moves forward.

Affordable housing

What people asked: Will the plan create homes that households below 80% of area median income can afford?

What the City said: The City says townhomes and multiplexes likely will not serve those households directly. It expects filtering, or "down-renting," to ease rent pressure later. Other strategies remain under consideration.

A clearer answer would say:

  1. Estimate how many homes the plan will produce in each income range. Separate zoning capacity from homes likely to be built.
  2. Estimate how much filtering will help, what evidence supports it, and how long it will take.
  3. Name the tools the City will use to build subsidized affordable homes and preserve lower-cost homes.
  4. Name the responsible departments and deadlines. Publish results. Say what changes if the targets are missed.